How Much Did This Thing Cost?
Derrick J Brashear
shadow at dementia.org
Mon Oct 23 14:53:46 EDT 2000
On Mon, 23 Oct 2000, Edward H. Lybarger wrote:
> Port Authority's current management inherited the West Busway project and
> fortuitously scaled it back. It has been open about 6 weeks now and is
> carrying 5400 weekday riders, 2200 on weekends. Wasn't it built at near-LRT
> prices? Shouldn't you be getting 30,000 or more weekday passengers if you
> pay that much?
For whatever number I saw I really figured there should have been wires
and rails; And I still like the duobus idea (run diesel/trolleybus
vehicles on the busways, drop the poles when you hit the streets at either
end, or maybe even string the wires downtown; makes the Edgewood whiners
happy: no noise, no pollution)
-D
More information about the Pittsburgh-railways
mailing list